9 Jan 2025 An Bord Pleanala Refuse Permission

The development will consist of the construction of 489 no. apartments, creche and offices in 5 no. blocks ranging in height from part-1 to part-8 no. storeys over lower ground and semi-basement podium levels. The proposed development is located adjacent to a Strategic Housing Development permitted by ABP-301991-18 and amended by ABP-310378-21 containing 6 no. blocks (Blocks 3, 4, 7, 8, 9 & 10) with existing Blocks 1, 2, 5 & 6 constructed on foot of T.P. 24609/00.

The development will contain 1 no. studio, 161 no. 1 bedroom apartments and 327 no. 2 bedroom apartments.

Block 11 is part-3 to part-6 no. storeys over semi-basement podium and lower ground levels and will contain 101 no. apartments.

Block 12 is part-1 to part-4 no. storeys over undercroft car parking and lower ground level office building (4,112 sq m) comprising 2,934 sq m of office floor area.

Block 13 is part-2 to part-8 no. storeys over lower ground levels and will contain a crèche over 2 no. levels (381 sq m) and 39 no. apartments.

Block 14 is part-3 to part-6 no. storeys over lower ground level and contains 130 no. apartments.

Block 15 is part-3 to part-6 no. storeys over semi-basement, podium and lower ground level and contains 219 no. apartments and ancillary resident amenity spaces (576 sq m).

Blocks 12 and 13 will contain ancillary commercial areas including a creche (381 sq m) and offices (4,112 sq m). The development will also contain supporting internal resident amenity spaces (576 sq m) and external communal amenity spaces.

The proposed development also provides for hard and soft landscaping, boundary treatments, public realm works, car parking, bicycle parking, bin stores, signage, lighting, PV panels, sprinkler and water tank, substations, plant rooms and all ancillary site development works above and below ground.

The application contains a statement setting out how the proposal will be consistent with the objectives of the Cork City Development Plan 2015 -2021 and the Draft Cork City Development Plan 2022 -2028, which will come into effect on August 8th, 2022.

The application contains a statement indicating why permission should be granted for the proposed development, having regard to a consideration specified in section 37(2)(b) of the Planning and Development Act, 2000, as amended, notwithstanding that the proposed development materially contravenes a relevant development plan or local area plan other than in relation to the zoning of the land.

An Environmental Impact Assessment Report and a Natura Impact Statement have been prepared in respect of the proposed development.

To find out more details on this Residential Development in Cork take the free trial here.

With full details of over 2,500 Residential Housing Projects worth in excess €11bn that are Granted Permission and ready to go Building Information Ireland is the best source of business intelligence for the Construction sector.
The intuitive and richly featured application is suitable for businesses of all sizes. 
 
The Mobile friendly app is ideal for and built for reps on the road. 
 
Take the free trial today and unlock the potential.
 
Mixed Development New Build in Cork


Address:
Jacob’s Island

Stage:
Plans Refused


Hundreds of similar projects available online.
Take a FREE trial.

FREE TRIAL