Construction of 130no. dwelling houses and all ancillary site works
The development will consist of the construction of 210 no. dwellings, creche, open space and ancillary infrastructure as follows:
A) 130 no. 2 storey houses (8 no. 2 bedroom houses, 106 no. 3 bedroom houses, & 16 no. 4 bedroom houses) in a mixture of semi-detached and terraced houses;
B) 80 no. duplex apartments/apartments (40 no. 2 bedroom apartments and 40 no. 3 bedroom duplex apartments) in a series of 5 no. duplex apartment buildings of 3 no. storeys in height, all duplex units to have balcony or terrace;
C) Creche of c. 524.7 sq. m (2 no. storeys) located to the south of (and with access from) the upgraded Poulgour Road along with associated car parking/cycle parking and open space;
D) Realignment and upgrade of a section of Poulgour Road (to include pedestrian crossing, vehicular, cycle and pedestrian access to site) to tie into William Robertson Way and Poulgour Road;
E) Open space areas (c. 1.66 ha), hard and soft landscaping (including public lighting) and open space (including boundary treatment), communal open space for duplex apartment/apartments; regrading/re-profiling of site where required along with bicycle/bin stores and ESB substations and use of existing structure (27.8 sq.m) as a bike store;
F) Bicycle (450 no. spaces) and car parking (429 no. spaces) as well as single storey bin and bicycle stores and internal roads including future link/distributor road [part] and pedestrian accesses to William Robertson Way;
G) Surface water attenuation measures and underground attenuation systems as well as connection to water supply, surface water drainage and provision of local pumping station to Irish Water specifications;
H) 2 no. temporary (for 3 years) marketing signage structures (c.4.5m in height, 3 sided c. 13.73 sq. m), [1 no. in proximity to William Robertson Way and the roundabout at Circular Road and 1 no. located in proximity to the junction of Poulgour Road and William Robertson Way];
I) All ancillary site development/construction
To find out more details on this Residential Development in Kilkenny Started on 30th September 2024 take the free trial here.