Amendment of permission granted under SD16A/0345 that will relocate the temporary gas powered generation plant from lands to the rear of the Takeda Ireland complex to the east of the site, to lands to the immediate north of Phase 1 data hall and single storey office granted under SD16A/0214 and to the south of the ESB substation and transformer yard that was permitted under SD16A/0345. The relocated temporary gas powered generation plant will be enclosed within a walled yard containing 12 generator units with associated flues (each 15m high). The development will also include new vehicular access to the temporary generator plant off the permitted service road as granted under SD16A/0214. The development will be enclosed with revised landscaping from that granted under SD16A/0214. An Environmental Impact Statement (EIS) has been submitted with this application.
To find out more details on this Light Industrial Development in Dublin Granted permission on 2017-04-04 take the free trial here.