A 10 year planning permission for a Grid Stability Development. The proposed development will comprise 2 no. control buildings, 120 no. containerised energy storage modules and associated plant and equipment, 20 no. power conversion system units, associated underground electrical ducting and electrical cabling to connect to a transformer/associated 100kV underground grid connection cabling to nearby Clashavoon substation (as previously permitted under Cork County Council reference 23/4541), access tracks, security fencing, landscaping, drainage and all associated ancillary development. Access to the proposed development will be via an entrance from the L7477 local road to the south (previously permitted under Cork County Council reference 23/4541)
To find out more details on this Power Generation Development in Cork Granted permission on 18th December 2024 take the free trial here.