Refurbishment and safety work to the Waterworks upper and lower reservoirs, and Alexandra Park Lake reservoir, to be complemented with wider environmental, landscape and connectivity improvements.
The reservoir works comprise of a new overflow structure with reinforcement and protection of the return embankment parallel to the by-wash channel at Waterworks Upper reservoir. Repairs to the upstream face of Waterworks Lower reservoir with the addition of wetland planting to reduce the overall capacity of the reservoir. Removal of an existing parapet wall and embankment reinforcement at the Alexandra Park Lake reservoir.
Improvements at Waterworks Park comprise the demolition of the existing Waterworks Bothy and replacement with a new building to include public toilets, Changing facilities, multi-purpose community room and kitchenette. Extension to existing Cavehill Road gatehouse building. Entrance improvements, new events space including multipurpose decking resurfacing of footways new pedestrian lighting along key routes a dog park replacement platforms and viewing area. New 3-on-3 basketball court replacement surface to existing small sided 3G pitch and upgrades to existing Queen Mary’s playground.
Improvements at Alexandra Park include the resurfacing of footways new pedestrian lighting along key routes new reinforced grass event space new lake viewing area new public toilets and changing places entrance improvements. 2no existing bridges replaced new pedestrian entrance reimagined peace wall new multi-sport synthetic surface with cover and upgrades to existing play parks.
Streetscape improvements along Camberwell Terrace and Castleton Gardens include resurfacing of footways with new kerbs resurfaced carriageways and new tactile paving at pedestrian crossings and all associated works.
To find out more details on this Water & Sewerage Development in Belfast Applied for on 20th December 2024 take the free trial here.