1) Demolition of the existing single storey school buildings (area c.3970m2) on the site
2) Construction of an 8,982m2 part one, two ,three storey replacement 600-pupil post-primary school building and associated facilities comprising of
i) 23 no. general classrooms, 6 no. specialist classrooms, 4 no. science laboratories, 3 no. technology rooms, 2no. art classrooms, 2 no. home economics classrooms, a 4 no. class base Special Education Needs unit
ii) A general or dining area, multi-use PE hall, library, administration offices, staff room, pupil social areas, fitness suite and changing room facilities
iii) Hard and soft landscaping to central external courtyard
iv) An external play area or sensory garden adjacent to the Special Education Needs unit
v) Installation of solar PV panels to the roof
3) All other associated site works required to facilitate the proposed development including
i) The provision of 4 no. hard play court areas
ii) The retention of an existing playing pitch and the retention of an existing all-weather sports surface
iii) The relocation of the vehicular entrance to the east of the existing vehicular entrance with provision of an air surface heat pump enclosure adjacent to the new school entrance
iv) The provision of 58 no. car-parking spaces including 6 no. accessible spaces, car set-down facilities and 172 no. bicycle parking spaces
v) Construction of a single storey bin store and ESB substation, and a separate LPG gas tank enclosure to the west of the school site
vi) Upgraded perimeter or boundary landscaping and fences
4) Works to public realm outside school site to include relocation of existing on-street carparking spaces to the east along Carrignafoy Avenue and new connecting footpaths.
To find out more details on this School Development in Cork Applied for on 23rd September 2025 take the free trial here.