1) The construction of a part 2 storey and part 3 storey post-primary school building comprising internal classrooms (16no.). Specialist teaching rooms, offices, special education needs base, double-height, multi-purpose room and ancillary accommodation on and access at the lower ground floor and ground floor levels
2) A 2-storey primary school comprising of 12 classrooms with 2 classroom SEN base, to accommodate the existing Gaelscoil, including learning, administration and ancillary spaces and a general purpose hall
3) Outdoor play areas and ballcourts with perimeter fencing, site lighting, an amphitheatre overlooking one of the ball courts, external heat pumps and LPG tanks enclosure, and anew ESB substation
4) Site works, including alteration of 2 no. existing vehicular entrances to L203 Cloghmacsimon public road, a new pedestrian site entrance, set-back from the N71 Bandon relief road, the relocation of existing onsite surface carparking and the provision of additional car parking spaces, roadworks, landscaping, site lighting, signage and all associated site works
5) The demolition of existing 4 no. ballcourts, a water storage tank, 810m2 of temporary prefabricated building, and ancillary hardstanding and landscaping
6) Minor alterations to the existing school and construction of 2 no. linking canopies
7) ESB cable division, at the site immediately south of and at Colaiste na Toirbhirte.
To find out more details on this School Development in Cork Applied for on 9th July 2025 take the free trial here.