9th May 25 Construction of i) a single storey building for use as electrical rooms for electronic operations, mechanical plant rooms and support areas including offices and welfare facilities, a loading bay, back up generators, 4 no. above ground water storage tanks, 53 car parking spaces and landscaping and associated ancillary works; 3 ancillary buildings consisting of ii) a single storey building storing MV electrical equipment; iii) an sprinkler pump room; iv) a security guard house.
Dec 24 Construction of a new Client Control Building & Construction of a new 110kV Gas Insulated Switchgear (GIS) Substation Building to service a new data centre
The proposed development at Kildare Innovation Campus involves a significant expansion, with a substantial focus on data center development.
Key Features:
Data Centers: Construction of four new data centers, featuring extensive floor space and significant mechanical and electrical infrastructure, including numerous fuel oil generators and cooling systems.
Deep Tech Buildings: Two new buildings dedicated to deep tech companies, fostering innovation and research.
Infrastructure:
New 110kV substation to support the increased energy demands.
On-site energy center with gas turbines for power generation.
Extensive car parking, including EV charging and a dedicated EV bus charging hub.
Significant cycle parking infrastructure.
New access roads, a public link road, and a pedestrian/cycle overpass across the M4 motorway.
Enhanced landscaping, security, and site services.
Sustainability Features:
Solar PV panels on buildings.
District heating system.
Green roofs on some buildings.
Environmental Considerations:
An Environmental Impact Assessment Report will be submitted with the planning application.
This development will significantly transform the Kildare Innovation Campus, positioning it as a major hub for data center operations and high-tech industries.
To find out more details on this Data Centre Development in Kildare Started on 12th December 2024 take the free trial here.