Planning permission for development at a site bounded by North Wall Quay, New Wapping Street, Mayor Street Upper and Castleforbes Road, Dublin 1 of c.1.875 ha. The development will consist of: demolition of ESB substation (c.50 sq.m) on Mayor Street Upper and partially completed basement structures; construction of a new office building (Block D) of 9 storeys (overall height +42.9m OD including set back top storey, atrium, core and plant) and 7 storeys (overall height +35.1m OD including set back top storey, atrium, core and plant) comprising a total of c.23,882 sq.m gross floor area above podium level; (Block D may operate as a single building or as two separate buildings D1 and D2); external terraces on the seventh and ninth storey of building D1 and seventh storey of building D2; new internal streets to the north, east and west of Block D; a two level basement comprising a total of c.34,680 sq.m gross floor area below ground level with a segregated ramp for bicycle and vehicular access from Castleforbes Road containing 4,360 sq.m of office space at Level -01 relating to Block D and 428 no. car parking spaces, 898 no. bicycle parking spaces, changing/shower toilet areas, storage, services and plant areas over Levels -01 and -02 to serve the proposed development and future development of the site as indicated within the Master Plan submitted with the application for the delivery of the remainder of City Block 8; landscaping works to the new internal streets to the north, west and east of Block D; temporary works and finishes (with fencing) to top of podium area which will be subject to future planning applications for office (Block A) and residential (Blocks B and E) development; temporary construction access to the north of the proposed permanent ramp access to the basement from Castleforbes Road; attenuation, foul and surface water arrangements, all associated site development boundary treatment, services provision and landscaping works. The total gross floor area above and below ground will be c.58,562 sq.m comprising 28,242 sq.m office use and 30,320 sq.m shared basement. This application relates to a proposed development within the North Lotts and Grand Canal Dock SDZ Planning Scheme Area.

This is a Nama-backed Project Wave Development.

Commencement 01/12/2015:
Initial works shall comprise of sheet piling, excavation & piling activity.

Commencement 04/04/2016:
Construction of a two level basement comprising a total of c.10,599 sq.m gross floor area below ground level, also to include podium level slab at ground floor level, relating to Block A of Project Wave. Initial works shall comprise of sheet piling, excavation & piling activity.

Commencement 14/07/2016:
Construction of a new office building (Block D) of 9 storeys (overall height +42.9m OD including set back top storey, atrium, core and plant) and 7 storeys (overall height +35.1m OD including set back top storey, atrium, core and plant) external terraces on the seventh and ninth storey of building D1 and seventh storey of building D2 (Block D may operate as a single building or as two separate buildings D1 and D2).

To find out more details on this Office Development in Dublin Started on 2015-12-01 take the free trial here.


Address:
Site bounded by North Wall Quay

Stage:
Commencement


Hundreds of similar projects available online.
Take a FREE trial.

FREE TRIAL