One
(1) 110kV substation with associated compound, including Two
(2) Single storey control and operational buildings, electrical plant, equipment, cabling, lighting, CCTV, lightning masts, diesel generator and diesel tank, security palisade fencing
• 2.45km underground electric cabling systems between the wind farm site and the proposed 110kV substation overlain with 5.5m wide stone access track
• 10.85km of 110kV underground electrical cabling from the proposed 110kV substation to the consented Bracklone 110kV substation including enabling works, services diversions, joint bays, along the grid route
• New entrance and access road to substation site from the R423.
• New clear span and box culvert or piped water course crossings
• Peat or spoil deposition areas and all associated felling, drainage and ancillary works necessary to facilitate the development. The applicant is seeking a ten-year permission for the purposes of construction of the proposed development as outlined above. An Environmental Impact Assessment Report (EIAR) and A Natura Impact Statement (NIS) have been prepared in relation to the project and accompanies the application www.dernacartwindfarmsid.ie

To find out more details on this Power Generation Development in Laois Applied for on 14th October 2024 take the free trial here.